Utshishkau – Sector 1
Saguenay-Lac-Saint-Jean
Sector 1 is about 540 km² and could generate 392 MW of wind power.

Sector 1 – 392 MW
The energy that’s produced will be sent to the existing Chamouchouane substation in La Doré.

Key project phases
- Fall 2025 and 2026
Project development (preliminary design).
Technical and environmental studies.
Filing of the project notification.
- 2026 and 2027
Filing of the environmental impact statement, BAPE process.
Government approvals.
- 2027 to 2030
Site clearing and construction
- 2030
Operation and maintenance
Interactive map
Use the interactive map to share your comments with us on the Utshishkau wind farm project.
Area map
The map shows the preliminary layout of the wind turbines in sector 1 of the Utshishkau wind farm project. This area could generate 392 MW of wind power. The energy that’s produced will be sent to Chamouchouane substation.
A few highlights:
72 potential wind farm sites are being studied. Depending on the study results and consultations, between 5 and 16 of them will be ruled out.
About 75% of the logging roads needed for the project are already built.
An underground collector system will run under the access roads.
This wind turbine layout plan is preliminary, so it may change based on the findings of the environmental and technical studies and discussions with local communities.
Preliminary Layout Plan


Let’s talk!
Do you have any ideas, suggestions, questions or comments about the Utshishkau wind farm project?
Info-Project Line:
1 833 822-3029- affairesregionales@hydroquebec.com
Wind energy resource development | Utshishkau area
Stay informed about the status of wind power development projects in this area.