Utshishkau – Sector 2

Saguenay-Lac-Saint-Jean

Sector 2 is also under study. It is about 306 km² and could generate 224 MW of wind power.

Sector 2 - 224 MW

The energy that’s produced will be sent to the existing Chamouchouane substation in La Doré.

Key project phases

  1. 2025 to 2029

    Preliminary project

  2. 2026 to 2029

    Government approvals, including the submission of the impact assessment

  3. 2029 to 2032

    Construction

  4. 2032

    Full commissioning

Area map

Sector 2 of the Utshishkau wind farm project covers about 306 km2 and could generate 224 MW of wind power. 

 

Before the preliminary turbine layout is established, several steps are needed: 

 

Environmental studies

Technical analyses

Discussions with communities 

 

Once the preliminary plan is finalized, it will be shared with the communities and discussed during the consultations. 

Preliminary Layout Plan

Preliminary Layout Plan

Let’s talk!

Do you have any ideas, suggestions, questions or comments about the Utshishkau wind farm project?

Wind energy resource development | Utshishkau area

Stay informed about the status of wind power development projects in this area.